Rehabilitation Progress:

  • Drywall and Painting: Completed.
  • Sound Deadening Panels: Installation happening in June 2024.

Upcoming Installations:

  • Hawthorn Room Lights: New lights have been chosen, purchased, and retrofitted. Installation is tentatively scheduled for June 10th.

Playschool Reopening:

  • Reopening Date: July 15th
  • Enrollment: All families that pre-registered for the summer program back in March/April will be returning.